Following the first re-conductoring project for 220kV Pha Lai – Pho Noi – Hai Duong TL of PTC1, we have successfully executed the second re-conductoring project for 110kV Dong Anh – Dinh Tram TL of NGC.
During a period of 3 months, from Jan. 22nd 2013 to Apr. 22nd 2013, we have proceed the contract for supply of over 35,000 m of ACCC 223 type Copenhagen and accessories for re-conductoring 110kV Dong Anh – Dinh Tram TL of NGC which fed the load of Samsung Electronic Vietnam (SEV). We have provided training, guidance and supervision of installation to customer in a period from Apr. 23rd 2013 to May 4th2013. The project was put into service in May 4th 2013.
This project had strict requirements on quality and schedule because it related to an important consumer of the utility (SEV). We have satisfied all the requirements resulting in highly appreciation of customer.